Breakdown of transferred assemblies by kind
- Spent fuel
- 1166 assemblies/1,331 assemblies
- Unirradiated
- New fuel22 assemblies/ 202 assemblies
- Number of times of cask transportation: 54 timesas of June.30,2014
*The fuel removal work is stopped from July 1 to earlySeptember of 2014 due to annual ceiling crane checkup
via TEPCO : Decommissioning Plan of Fukushima Daiichi Nuclear Power.